Wednesday, April 30, 2008
Tuesday, April 29, 2008
Friday, April 25, 2008
Frame work




In a busy five days, the frame of the building is now almost complete. You can already get a really good idea of what the space will be like inside - and what it will look like in terms of size from the outside. I have taken a few pictures from different angles (from the existing road, from the eastern property line and from the back of the West lodge) to give you an idea of how it fits into the landscape. Click on the pictures to enlarge. It is really well screened by trees so I think will be quite low impact visually. A crew of four very hard workers here six days a week and expected completion is a total of five weeks - so another month...
Wednesday, April 23, 2008
First post in...
Work on manager's residence started on Monday and here are a couple of pictures to show. We are using the base of a previous water cistern as a footprint. Foundations and floor joists are already in place and first stud wall raised about 20 minutes ago! More pictures soon.
Fingers crossed, touch wood etc but RECO energy problems have diminished greatly in the last two weeks with only occasional 2-3 hour outages. All hoping things continue in the same direction.
Thursday, April 17, 2008
Delay...
Building now commences Monday 21st. Leston had an accident at another site on Tuesday but will be fighting fit to start on Monday.